Sheriff Avenue Reconstruction Project
Project Name:
      Sheriff Avenue Reconstruction Project

Project Location:
      Sheriff Avenue from North Market Street to North 3rd Street

Project Description:
This project consisted of the reconstruction of Sheriff Avenue (31 foot wide concrete pavement) from North Market Street to North 3rd Street.  In addition to the street pavement, driveway approaches along the project were replaced and improvements were made to the storm sewer.

Project Benefits:
The benefits of this project include new 8 inch thick concrete street pavement and storm sewer improvements.  Click on the link below to view the project plans.


Project Status:
This project was awarded to DeLong Construction Inc. on April 3, 2017 for $472,100.75 with a total contingency of $24,785.00.  Construction began on May 30th and the project was substantially completed on August 23rd. 

Project Costs:
Design & Inspection:       $83,000.00
Construction:                 $467,647.38
Total Cost:                    $550,647.38

Construction Start Date:
5/30/2017
Construction End Date:
8/23/2017