C Avenue East Pavement Rehabilitation Project
Project Name:
North C Street Curb and Gutter Replacement Project

Project Location:
North C Street from C Avenue West to College Avenue


Project Description:
  • This project involves the construction of new concrete curb and gutter, ADA sidewalk and ramps, storm sewer improvements, and alley and driveway approach improvements 
  • This project is scheduled to begin in July or August of 2017 and last for 40 working days.  

Project Benefits:
The existing block style curb has deteriorated and will be replaced with new 2' wide, 8" thick concrete curb and gutter.  The new curb will improve safety and stormwater flow along North C Street.  In addition, the ADA sidewalk improvements at the intersection of D Avenue West will provide greater pedestrian access and mobility.


Project Status:
This project was opened for bidding effective April 18, 2017, with the bid opening scheduled for May 5, 2017 at 10:00 am.  A public meeting to discuss the scope and schedule in more detail has been set for Thursday, April 27, 2017 at 6:00 pm on the 3rd floor of the Oskaloosa Public Library.

Estimated Project Cost: $158,200

Estimated Construction Start Date:
07/15/2017
Estimated Construction End Date:
10/31/2017

Project Completion
It is anticipated that this project will be completed by the end of October of 2017.     